How to Prepare Your Facility for a Solar or Hybrid Installation in 30 Days
Nigerian C&I managers can fast-track solar readiness with this proven 4-week checklist. Facilities that complete prep work upfront cut EPC timelines from 120 to 90 days and avoid ₦20M+ in change orders.
Week 1: Data Collection (Baseline Locked)
Meter Your Reality (7 Days Mandatory)
text□ Total kWh: Main meter log (8AM-6PM vs 6PM-6AM daily) □ Diesel: Tank gauge + genset hour meter (liters/day confirmed) □ Grid: Voltage logger (sags <400V?), outage hours/week □ Circuits: 3-phase vs single-phase split (HVAC separate)
Quick Wins:
Export data to Excel (template on request)
Photos: Roof access points, parapets, electrical room
Current bill: Last 3 months tariffs + diesel invoices
Week 2: Physical Site Assessment
Roof Reality Check:
text□ Available area: Google Earth polygon (min 1,000m²/MW) □ Load capacity: Engineer confirms 20kg/m² panels + wind □ Shading: Trees/chimneys/parapets (drone survey ₦500k) □ Access: Crane path, worker safety (fall protection ready)
Electrical Room Audit:
text□ Space: 20m²/MW inverter room (dust-proof, ventilated) □ Switchboard: 415V 3-phase spare breakers □ Earthing: 300m grid exists? Lightning protection?
Week 3: Approvals & Clearances
Fast-Track Permitting:
text□ NERC: Embedded generation application (≤1MW = 30 days) □ State ESD: Lagos/Ogun clearance (14 days with agent) □ Fire: Panel spacing certificate (0.5m edges minimum) □ Landlord: Estate approval (Lekki/VGC common delay)
Internal Alignment:
text□ Capex approval: CFO signs off 3 financing options □ FM team: Nominated for 2-day training □ Tenants: MOUs for multi-building sites
Week 4: Commercial Lock-In
Financing Decision:
text□ Cash >₦500M? → Equity (38% IRR) □ Need fast ROI? → PPA ₦48/kWh fixed □ SME? → CBN green loan 9% × 5 years
EPC Contract Ready:
text□ Fixed price: ₦450M/MW all-in (no escalation) □ Timeline: 90 days to commissioning □ Performance: 82% PR guarantee Month 1 □ Storage-ready: Pre-wired DC bus Year 3 expansion
Common 30-Day Pitfalls (Avoid These)
| Mistake | Cost Impact | Fix |
|---|---|---|
| No meter data | +12 weeks delay | Week 1 mandatory |
| Roof fails load | +₦65M reinforcement | Week 2 engineer |
| NERC permit late | +60 days grid sync | Week 3 agent |
| FM team missing | 14-day downtime | Week 3 nominate |
Your 30-Day Deliverables Checklist
text□ [ ] 7-day meter data exported □ [ ] Roof engineer report □ [ ] NERC application submitted □ [ ] Financing term sheet signed □ [ ] FM team nominated □ [ ] EPC contract ready to execute
Lagos Factory Result: Week 1 prep → Day 85 commissioning vs 165 days average.
Upthrust 30-Day Accelerator: Complete this checklist → we guarantee 90-day EPC start or credit your deposit.
Upload your Week 1 meter data today—get complete roadmap + savings projection in 24 hours.