Inside a Successful C&I Solar Project: From Feasibility Study to Commissioning
Follow this proven 90-day roadmap used by Upthrust to deliver 25MW+ across Nigerian factories, malls, and estates—guaranteed 40% diesel savings.
Phase 1: Feasibility Study (Days 1-14)
Week 1 - Data Collection:
text- 7-day kWh meter log (day/night split) - Diesel liters + runtime hours - Roof survey: 1,200m²/MW @ 15kg/m² load - Grid voltage log, outage frequency
Week 2 - Financial Model:
text1MW example → 1.46M kWh/year @ ₦38/kWh LCOE Diesel baseline: ₦120/kWh → ₦120M annual savings Payback: 3.8 years, IRR 38% PPA option: ₦48/kWh fixed, zero capex
Deliverable: Bankable techno-economic report + 3 financing options
Phase 2: Design & Permitting (Days 15-45)
Technical Design:
text- DC: 1.2MW bifacial panels (20% oversize) - AC: 1MW hybrid inverters (150% overload) - Storage-ready: Spare DC strings, EMS protocols - Single-line diagram for NERC approval
Regulatory Fast-Track:
NERC embedded generation permit (≤1MW = 30 days)
Lagos/Ogun ESD clearance (14 days)
Fire certificate (panel spacing, earthing)
Bi-directional metering specification
Procurement Lock:
Tier 1 panels (Jinko/Trina): 25yr warranty
SMA/Fronius inverters: 10yr warranty
Local content: 40% Nigerian EPC labor
Phase 3: EPC Execution (Days 46-80)
Civil Works (2 weeks):
textRoof: Waterproofing, racking (25° tilt) Ground: Concrete pads, security fencing Electrical: Earthing grid, lightning arrestors
DC Installation (3 weeks):
2,200 panels, string optimization
IV curve testing per string
DC isolators, weatherproof combiners
AC Commissioning (2 weeks):
textInverter room (AC/HVAC ready for batteries) Main switchboard integration SCADA + cloud monitoring live Full-load simulation test
Phase 4: Go-Live & Handover (Days 81-90)
Performance Verification:
text- 72hr stability test (grid on/off) - PR >82% first month guarantee - Zero string mismatch - Remote monitoring handover training
Operations Launch:
textMonthly savings report template Quarterly cleaning schedule Annual thermography protocol 15yr O&M escalation: 3% max
Real Lagos Factory Timeline (1MW)
textDay 1: Contract signed Day 14: Financing approved, NERC permit Day 45: First panel lands Apapa Day 75: Grid synchronized Day 90: ₦10M first month savings verified
Upthrust Turnkey Guarantee: Fixed price, fixed timeline, 40% diesel reduction or we work free until achieved.